Over the past four years, we have been engaging with Blaby District council, local parishes, statutory stakeholders and members of the community to help shape the vision for the proposed new communities.
The timeline below provides an overview of the engagement activities undertaken to date and proposed engagement over the next year.
October 2021
Inaugural Community Vision Workshop
December 2021
Further Community Workshops
April 2022
Community Liaison Group Launch
May 2022
Community Liaison Group Meeting #1: New settlement identity development
August 2022
Community Liaison Group: Site walk & Meeting #2: Highways
October 2022
Community Liaison Group Meeting #3: Design Development
December 2022
End of Year Report published
January 2023
Community Liaison Group Meeting #4: Meet the Transport Planner
June 2023
Community Liaison Group Meeting #5: Early Masterplan vision
December 2023
End of Year Report published
Spring 2024
Parish Council Roadshow
October 2024
Community consultation event hosted by Stoney Stanton Parish Council
May 2025
Community Liaison Group Meeting #6: EIA Process
June 2025
EIA scoping request submitted
Spring 2026
– Blaby District Council Regulation 19 public consultation (anticipated)
– CLG meeting 7 on Highways and Drainage (Date TBC)
– CLG meeting 8 to discuss the Regulation 19 consultation plan
Summer 2026
– Public consultation on the outline planning application (Webinar and in-person events)
– CLG meeting 9 on the proposed submission plans
– Estimated submission of the outline planning application to BDC